Summary: A failed expansion joint on the A406 reported in the morning, repaired the same night and open to traffic before the Monday morning peak.
The challenge
A defective expansion joint on the A406 needed immediate attention to stop it deteriorating further and to keep the road safe to use. The client called us in the morning, and with the urgency and traffic volumes on this strategic route, a same-day fix was essential.
Traditional repair methods would have meant extended closures and long curing times, which simply weren't possible on a busy Sunday leading into the Monday morning rush hour. The repair had to go in overnight and take heavy traffic by morning.
The solution
Elastomac was chosen as the quickest and most effective intervention. Our team mobilised the same night and carried out a layered installation, letting each lift cool and stabilise before applying the next.
This controlled, staged approach gave the repair the strength and durability it needed while still meeting the tight overnight programme. Thanks to Elastomac's rapid curing, the section was fully ready for traffic ahead of the Monday morning peak.
Results
One of London's busiest corridors stayed open, with the joint repaired and trafficked before the morning rush.
- Same-day mobilisation meant an immediate response to a critical joint failure on the A406
- Layered installation allowed controlled cooling and optimal performance under heavy traffic
- Rapid return to service meant the road reopened in time for the morning rush hour
Frequently asked questions
Where was this emergency elastomac repair carried out?
A406 North Circular, London, for Local authority.
How long did the works take?
One night.
Why was this method used?
Elastomac was chosen as the quickest and most effective intervention. Our team mobilised the same night and carried out a layered installation, letting each lift cool and stabilise before applying the next.
What was the result?
One of London's busiest corridors stayed open, with the joint repaired and trafficked before the morning rush.
Related: Elastomac permanent repairs · Climate funding guide · All case studies
Full case study (PDF)
Project Overview
Platinum 3Sixty delivered a specialist expansion joint intervention on the A406, helping protect the carriageway, improve durability and reduce future maintenance requirements.
The repair was completed with a focus on long-term performance, controlled installation and minimal disruption on a busy strategic route.
Key Benefits
Strategic Route Repair
Delivered on the A406, one of London’s key highway routes.
Joint Protection
Intervention designed to protect the joint area and surrounding carriageway.
Reduced Maintenance
Durable repair approach helping reduce repeat intervention.
Minimal Disruption
Efficient delivery helped limit impact on road users.