A406 North Circular Rd (Sterling Way) – Concrete Repair

Case Study

Summary: Reflective cracking and failed joints on the A406 concrete carriageway repaired in-situ with Elastomac over four nights, avoiding costly slab replacement.

590 m²both carriageways
4 nightsdelivery
Noexcavation or muck-away
Over 90%carbon reduction

The challenge

The A406 Sterling Way is a concrete carriageway, which is difficult and disruptive to repair in London. Concrete works need deep excavation, muck-away and long curing times, which means high costs, extended traffic management and major disruption.

This section had reflective cracking and joint failure. Asphalt patching had only given temporary relief, and full concrete replacement was too costly and time-consuming for short overnight lane closures.

The solution

Working for TKJV, Platinum 3Sixty trialled a faster, more sustainable solution: a hot-applied, in-situ Roadmender Elastomac repair applied directly onto the concrete. This method:

Results

By extending the life of the existing concrete, the repair reduced future interventions, disruption and long-term cost.

Follow-up: still in service on the North Circular

Sterling Way at Bull Lane is an exposed concrete section of the A406. Historic asphalt patches across the slab joints had already failed, leaving reflective cracking and a route for water. A conventional concrete repair means cutting out the slab, reinstating and protecting it while it cures – a poor fit for short overnight lane closures.

The Elastomac repair remained visibly identifiable and in service at the first follow-up, and the surrounding concrete carriageway was kept rather than replaced. Peak-hour flows on this link exceed 5,000 vehicles an hour in each peak.

Frequently asked questions

Where was this elastomac concrete repair carried out?

A406 Sterling Way at Bull Lane, London (North Middlesex University Hospital access), for TKJV.

How long did the works take?

4 nights.

Why was this method used?

Working for TKJV, Platinum 3Sixty trialled a faster, more sustainable solution: a hot-applied, in-situ Roadmender Elastomac repair applied directly onto the concrete. This method:

What was the result?

By extending the life of the existing concrete, the repair reduced future interventions, disruption and long-term cost.

Has the repair lasted?

Sterling Way at Bull Lane is an exposed concrete section of the A406. Historic asphalt patches across the slab joints had already failed, leaving reflective cracking and a route for water. A conventional concrete repair means cutting out the slab, reinstating and protecting it while it cures – a poor fit for short overnight lane closures.