Eurotunnel – Pothole Repair

Case Study

Download PDF

Summary: Permanent Elastomac repairs to four potholes on a live Eurotunnel freight lane, completed between shuttle arrivals with zero delay to the timetable.

4potholes repaired
20 minworking windows
One nightdelivery
Zerotimetable delays

The challenge

Freight shuttles were unloading articulated lorries every 20 minutes, creating a strict operational cycle. Any overrun would disrupt Eurotunnel's live freight timetable.

The solution

Elastomac was the right fit for every constraint on this site:

Results

Four permanent repairs in a live freight environment, with zero delays to the timetable.

Frequently asked questions

Where was this emergency elastomac repair carried out?

Freight lane, Folkestone terminal, for Eurotunnel Group.

How long did the works take?

One night.

Why was this method used?

Elastomac was the right fit for every constraint on this site:

What was the result?

Four permanent repairs in a live freight environment, with zero delays to the timetable.