Completed Elastomac wheel-track repair on Sopwith Way, Kingston upon Thames

Elastomac Road Repair - Sopwith Way, Kingston upon Thames

Targeted Wheel-Track & Carriageway Repairs

Download Case Study PDF

Summary: Targeted Elastomac repairs to longitudinal wheel-track deterioration on a busy Kingston town-centre route, with extra defects treated while the team was mobilised.

Wheel trackprincipal defect
July 2026delivery
28,426vehicles a day
One TMset-up used

The challenge

Sopwith Way had longitudinal deterioration in the vehicle wheel tracks, with further localised failures across the wider carriageway becoming apparent during the works.

As a busy town-centre route carrying over 28,000 vehicles a day, the works had to be done at night under traffic management, and any second visit would mean another set-up and more disruption.

The solution

Platinum 3Sixty treated the principal wheel-track failure with Elastomac and took in the wider carriageway defects while already mobilised, getting more repair value from the same traffic-management set-up.

Treatment was focused where the carriageway was actually failing, avoiding unnecessary excavation while improving the surface through the most heavily trafficked areas.

Results

A continuous wheel-track repair, with the wider carriageway treatment tied in where failures were found.

Frequently asked questions

Where was this elastomac road repair carried out?

Sopwith Way, Kingston upon Thames, for Local authority highways.

How long did the works take?

July 2026, night-time traffic management.

Why was this method used?

Platinum 3Sixty treated the principal wheel-track failure with Elastomac and took in the wider carriageway defects while already mobilised, getting more repair value from the same traffic-management set-up.

What was the result?

A continuous wheel-track repair, with the wider carriageway treatment tied in where failures were found.

Related: Elastomac permanent repairs · Climate funding guide · All case studies

Full case study (PDF)

Project Overview

Platinum 3Sixty delivered targeted Elastomac road repairs on Sopwith Way in Kingston upon Thames, treating longitudinal deterioration within the vehicle wheel tracks and additional localised carriageway failures identified while the team was already mobilised.

The works were delivered during July 2026 under night-time traffic management on a live town-centre route. The case study records 2023 AADF traffic data of 28,426 vehicles per day, highlighting the importance of a focused repair approach on a heavily trafficked section of carriageway.

July 2026Delivery period
Wheel-track repairsPrincipal defects
Town-centre routeLive highway environment
28,426 vehicles/day2023 AADF data

The Problem: Longitudinal Wheel-Track Failure

Sopwith Way showed longitudinal deterioration through the vehicle wheel tracks. During delivery, further localised failures across the carriageway also became apparent, creating an opportunity to address more of the deteriorated surface within the same traffic-management setup.

The Response: Targeted Elastomac Carriageway Repairs

Platinum 3Sixty treated the principal wheel-track failure and incorporated the wider carriageway defects while the team was already on site. This allowed the additional failures to be dealt with during the same mobilisation rather than leaving them for a separate intervention.

Targeted Treatment

Repair activity was concentrated on the areas where the carriageway was visibly failing.

One Mobilisation

Additional carriageway defects were incorporated while the existing traffic-management setup was already in place.

Reduced Excavation

The approach focused treatment where required, reducing unnecessary excavation across unaffected areas.

Night-Time Delivery

The repairs were delivered under night-time traffic management on a live town-centre highway.

Before, Repair Areas & Completed Works

The photographs below show the original wheel-track deterioration and wider carriageway defects, the marked repair area, and the completed Elastomac treatment.

Project Outcome

The completed works produced a continuous wheel-track repair with wider carriageway treatment tied in where additional failures had been identified. The project addressed the principal wheel-track deterioration while making use of the existing mobilisation and night-time traffic management to treat further defects.

Why this repair approach mattered

By focusing the treatment on the failing areas of the carriageway, the works reduced unnecessary excavation while improving the surface through the most heavily trafficked areas of Sopwith Way.

Elastomac Highway Repair in Kingston upon Thames

This Sopwith Way project is one example of Platinum 3Sixty's approach to targeted highway maintenance using Elastomac. For more information about the repair system, visit the Elastomac service page, or explore more highway maintenance case studies.