Summary: Repeat Elastomac repair visits on the Thanet Earth internal access road since July 2025, treating failures where they occur and keeping the route open for HGV and operational traffic.
The challenge
The internal access road serves a busy horticultural and industrial site and has to stay dependable under regular HGV traffic. Localised failures had developed across the route, including on high-stress bends.
Wider resurfacing would have meant cost and disruption the site did not need, and the road had to stay open for operations throughout.
The solution
After a first visit in July 2025, Platinum 3Sixty delivered a programme of targeted Elastomac repairs, working at night to keep the route open: three night shifts totalling 377 m² in August 2025 and a further 188 m² over two nights in November 2026.
Treating the failed areas rather than resurfacing the whole road kept disruption down and improved the surface where intervention was needed most, with repaired areas back in use within minutes.
Results
Over 580 m² of permanent repairs delivered around a live site, with zero downtime and the client coming back for more.
- Targeted repairs avoid unnecessary wider resurfacing
- Night working kept the route open for operational traffic
- Performance holds up on high-stress bends under HGV loading
12 months on: still sound on a high-stress bend
The repair on this bend continues to present well about a year after installation. Despite being on a high-stress section with turning HGVs, the treated area remains visibly stable and in service.
It gives a clear visual record after 12 months of live use, and the site has since brought us back for a further 188 m² of repairs.
Frequently asked questions
Where was this elastomac road repair carried out?
Thanet Earth internal access road, Barrow Man Road, Kent CT7 0AX, for Thanet Earth.
Why was this method used?
After a first visit in July 2025, Platinum 3Sixty delivered a programme of targeted Elastomac repairs, working at night to keep the route open: three night shifts totalling 377 m² in August 2025 and a further 188 m² over two nights in November 2026.
What was the result?
Over 580 m² of permanent repairs delivered around a live site, with zero downtime and the client coming back for more.
Has the repair lasted?
The repair on this bend continues to present well about a year after installation. Despite being on a high-stress section with turning HGVs, the treated area remains visibly stable and in service.